PMP Question 2


Halfway through the project, a significant client request necessitates a shift in project priorities. This change could impact the timeline and resource allocation. You schedule a meeting with key stakeholders and team leads to discuss the way forward.

In negotiating the shift in project priorities, what principle should guide your approach?

A) Insisting on the original plan to avoid setting a precedent for client-driven changes, maintaining project scope and deadlines.

B) Focusing solely on the additional revenue the change request brings, prioritizing any tasks that increase project budget.

C) Balancing the client’s needs with the project’s scope and resources, seeking a compromise that aligns with team capabilities and project goals.

D) Automatically accepting the client’s request, reallocating resources to new priorities without reviewing the impact on the project’s original goals.


As we face unexpected shifts in our project landscape, the art of negotiation becomes our most valuable tool. It’s not about saying ‘yes’ to every request or rigidly sticking to our original plan. Instead, it’s about finding that sweet spot where we can adjust our sails to accommodate new winds without losing direction. This approach ensures that we remain responsive to our client’s needs while safeguarding the project’s integrity and team morale. Through open dialogue and strategic compromise, we navigate these challenges, ensuring our project remains on a course for success.


Correct Answer: C

Reason: Effective negotiation involves finding a balance between various project constraints and opportunities, ensuring that changes are manageable and beneficial.

Incorrect Answers:

A) Insisting on the original plan without flexibility can lead to missed opportunities and client dissatisfaction.

B) Prioritizing changes solely based on additional revenue without considering project impact can derail the project.

D) Automatically accepting client requests without assessing impact can compromise project goals and team morale.