The Myth of Resilience

In today’s world, we’re constantly bombarded with messages about the importance of resilience. Headlines proclaim that resilience is crucial for success, that we need to cultivate it, and that without it, we’re doomed to fail. But what if I told you that resilience isn’t what we really need?

Subscribe to get access

Read more of this content when you subscribe today.


4 PMP Questions about the Article

Question 1

A project manager is leading a large-scale organizational change initiative. The company has been proud of its ability to weather economic downturns in the past, but is now struggling with rapid technological changes. Which of the following approaches would be most appropriate for the project manager to recommend?

Subscribe to get access

Read more of this content when you subscribe today.

Question 2

During a project retrospective, a team member suggests that the team needs to focus on becoming more resilient to handle future challenges. As the project manager, how should you respond to this suggestion?

Subscribe to get access

Read more of this content when you subscribe today.

Question 3

A project manager is leading a team through a period of significant organizational change. Which of the following approaches best aligns with the article’s recommendations for handling challenges?

Subscribe to get access

Read more of this content when you subscribe today.

Question 4

During a project affected by unexpected external factors, a stakeholder insists that the team needs to be more resilient. Based on the article’s perspective, what would be the most appropriate response from the project manager?

Subscribe to get access

Read more of this content when you subscribe today.


Answer 1

Subscribe to get access

Read more of this content when you subscribe today.

Answer 2

Subscribe to get access

Read more of this content when you subscribe today.

Answer 3

Subscribe to get access

Read more of this content when you subscribe today.

Answer 4

Subscribe to get access

Read more of this content when you subscribe today.


Buy Scrum Fundamentals on Etsy.com – Promo code: SUMMER24

Buy PMP Questions 1-100 on Etsy.com – Promo code: SUMMER24

PMP Questions 51-60

pmp exam questions
Photo by Teona Swift on Pexels.com

PMP Question 51

At a critical milestone in a development project, it is determined that implementation is two months behind schedule. The project manager is concerned that the root cause is lack of conformance to requirements in the design of the new billing system. More extensive measurements are taken to see if this is, in fact, the problem. Those measurements are:

Explanation about the question:


PMP Question 52

Which of them is the act of adding detail, order, and size to items in the Product Backlog?

Explanation about the question:

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


PMP Question 53

How much time should the Product Owner dedicate to managing the Product Backlog?

Member Content

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Explanation about the question:

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


PMP Question 54

Which technique allows large numbers of ideas to be sorted into groups for review and analysis?

Explanation about the question:

The Options

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


PMP Question 55

According to the Agile Manifesto, which of the following describes the more valued items?

Explanation about the question:


PMP Question 56

You’ve been appointed as the new project manager for a critical project that is already underway. Upon reviewing the project’s progress, you discover that not only is the project significantly behind schedule, but also that the budget has been exceeded by 30%. Furthermore, you find evidence suggesting that key project requirements were misunderstood in the initial planning phase, leading to a substantial rework effort.

Despite these challenges, the previous project manager has consistently reported to the sponsor that the project is progressing smoothly and is on track to meet its objectives. What is the MOST appropriate course of action for you to take?

Explanation about the question:


PMP Question 57

Which of the following is the best reason that PMI publishes a Code of Ethics?

Explanation about the question:


PMP Question 58

You have just assigned as a project manager with core team members. You asked your members to work on the process of defining stakeholders to create a model  with multiple dimensions that improves the depiction of the stakeholder community. They started to discuss about the technique that they should use to create the model. Which technique is the best to create this model?

Explanation about the question:


PMP Question 59

If resource planning is done at an early stage, what is the latest point at which resource assignments are usually confirmed and start and finish dates are usually established?

Explanation about the question:


PMP Question 60

During a software development project, a project stakeholder expresses repeated concerns about a specific feature developed by the team, stating that it does not align with the original design specifications. Despite several clarifications from the development team, the stakeholder remains unsatisfied and insists that the feature is not meeting the intended requirements. How should the project manager address this issue to ensure alignment with the project scope?

Explanation about the question:

PMP Questions 41-50

Question 41

Who is accountable for the Product Backlog when it comes to content and order?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 42

A customer is requiring a minor scope change and expects you to do this without delays and additional costs. You believe that you have adequate authorization to make the decision by yourself, but you are not quite sure. What should be your next steps?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 43

In the middle of the project, your project sponsor has asked you, “What do we expect the total project cost, now?” Which of them should you use to answer?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 44

Which of the following qualities should a project manager prioritize when assessing the consistency and reproducibility of repeated measurements or actions within a project?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 45

David is a project manager working for a prominent book publishing company. As the most senior project manager within the organization, he often gets paired with strong- willed project sponsors. During a recent project meeting, David’s project sponsor began yelling in frustration at the project’s status, which was blocked because of a critical resource being out ill. In frustration, the sponsor began spewing profanities at David, questioning his ability to manage effectively. In response, David calmly assured the project sponsor that a contingency plan would be implemented and requested that they speak privately to address his frustrations. David then excused the rest of the project team. What core value did David uphold during the meeting?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 46

You took over a new project. The previous project manager completed some of the WBS. When you begin to define the project activities, you realize that the WBS work packages expected to occur in the next year are planned in detail, but the work packages for later in the future are not planned with much detail, if any detail at all. You determine:

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 47

A new regulation requires consumer warnings on labels, but a company’s product package is too small to fit the added information. The regulatory specification does not provide a solution, so the agile team decides to solve the problem by displaying the information on a fold-out flap. The start of mass production of the new labels, the project’s next milestone, is scheduled to begin in five days. What should the agile team do next?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 48

In which of the following methods of resolving conflict, will the conflict typically reappear again?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Question 49

You are very interested in becoming a project manager. You have been mentored with other experienced project managers in your organization to learn more about how to be an effective project manager. You’ve been told your organizational skills and communication skills are excellent. However, you need some additional training in accounting and budgeting skills, because you are weak in these general management areas. The mentor who was honest enough to tell you this explained it which of the following ways?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 50

A project manager is preparing to send five engineers to Japan to install a high-security network. The engineers have never been outside of the United States before. Prior to their travel, the project manager asks the Japan-based manager to give the engineers an overview of their history, customs, and social norms. What is the primary objective of the project manager in this situation?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

PMP Question 8

In the context of effective resource management planning, why is it crucial to maintain a pool of external resources such as freelancers or consultants?

A) It fosters a continuous influx of innovative ideas and diverse perspectives, enhancing the project’s creativity and adaptability.

B) External resources often possess specialized skills and expertise, making them more adept at handling intricate project tasks with efficiency.

C) Utilizing external resources tends to be a more financially prudent approach than investing in training existing staff for transient or specialized roles.

D) They serve as a reliable contingency plan, providing supplementary support during periods of heightened workloads or unforeseen resource scarcities, thereby ensuring uninterrupted project progression.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

PMP Question 5

The project you’re managing involves collaboration between teams from two different companies with distinct corporate cultures. To unify the teams, you recognize the need to establish common team norms.

What approach do you take to establish effective team norms for this collaborative project?

A) Drafting a set of norms based on your company’s culture and enforcing them across the combined team to maintain consistency.

B) Holding a joint workshop where team members from both companies can contribute to the creation of shared norms, ensuring buy-in from all participants.

C) Allowing each company to follow its own set of norms to avoid conflict, relying on project milestones to keep the teams aligned.

D) Deciding that establishing team norms is too time-consuming and unnecessary, focusing instead on individual accountability for project deliverables.


When two distinct corporate cultures come together for a project, the potential for innovation is boundless. Yet, this fusion can also present challenges in alignment and collaboration. By engaging both teams in the creation of shared norms, we’re not just building a set of rules; we’re crafting a new, shared culture that honors the diversity of our combined team. This collaborative approach ensures buy-in from all members, creating a foundation of mutual respect and shared commitment. As we navigate this journey together, these norms become our compass, guiding us toward a successful collaboration that leverages the strengths of both companies.


Correct Answer: B

Reason: This inclusive approach ensures that norms reflect the combined team’s values and working styles, fostering unity and collaboration.

Incorrect Answers:

A) Imposing one company’s norms can create resistance and diminish the value of collaboration.

C) Allowing each company to follow its norms can lead to confusion and inefficiencies.

D) Neglecting to establish team norms overlooks the opportunity to create a cohesive team culture, potentially leading to misunderstandings and conflict.