PMP Questions 51-60


pmp exam questions
Photo by Teona Swift on Pexels.com

PMP Question 51

At a critical milestone in a development project, it is determined that implementation is two months behind schedule. The project manager is concerned that the root cause is lack of conformance to requirements in the design of the new billing system. More extensive measurements are taken to see if this is, in fact, the problem. Those measurements are:

Explanation about the question:


PMP Question 52

Which of them is the act of adding detail, order, and size to items in the Product Backlog?

Explanation about the question:

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


PMP Question 53

How much time should the Product Owner dedicate to managing the Product Backlog?

Member Content

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Explanation about the question:

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


PMP Question 54

Which technique allows large numbers of ideas to be sorted into groups for review and analysis?

Explanation about the question:

The Options

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


PMP Question 55

According to the Agile Manifesto, which of the following describes the more valued items?

Explanation about the question:


PMP Question 56

You’ve been appointed as the new project manager for a critical project that is already underway. Upon reviewing the project’s progress, you discover that not only is the project significantly behind schedule, but also that the budget has been exceeded by 30%. Furthermore, you find evidence suggesting that key project requirements were misunderstood in the initial planning phase, leading to a substantial rework effort.

Despite these challenges, the previous project manager has consistently reported to the sponsor that the project is progressing smoothly and is on track to meet its objectives. What is the MOST appropriate course of action for you to take?

Explanation about the question:


PMP Question 57

Which of the following is the best reason that PMI publishes a Code of Ethics?

Explanation about the question:


PMP Question 58

You have just assigned as a project manager with core team members. You asked your members to work on the process of defining stakeholders to create a model  with multiple dimensions that improves the depiction of the stakeholder community. They started to discuss about the technique that they should use to create the model. Which technique is the best to create this model?

Explanation about the question:


PMP Question 59

If resource planning is done at an early stage, what is the latest point at which resource assignments are usually confirmed and start and finish dates are usually established?

Explanation about the question:


PMP Question 60

During a software development project, a project stakeholder expresses repeated concerns about a specific feature developed by the team, stating that it does not align with the original design specifications. Despite several clarifications from the development team, the stakeholder remains unsatisfied and insists that the feature is not meeting the intended requirements. How should the project manager address this issue to ensure alignment with the project scope?

Explanation about the question: